Fixed-Price Project in AX 2012 R2

This question is answered

Hi All,

I want to know how to post cost and sales based on %completion in fixed price project. I saw there is a tab in fixed price project in AX 2012 R2 about "Completed percentage", but i am not sure how to play with this.

Any help on this will be very helpful,

Thanks,

Gaurav Chandak

Verified Answer
  • Hi Gaurav,

    The PoC is being calculated and posted by use of Estimate Projects. There is some setup to do and understanding how it exactly works.

    It's too much for a reply like this...

    I fyou have access to training material of AX2012, the training Projects - Advanced handles this topic.

    kind regards,

    André Arnaud de Calavon  |  Microsoft Dynamics AX Solution architect  |  My blog  |  My company

    This post is my own opinion and does not necessarily reflect the opinion or view of my company, Microsoft, both its employees, or other MVPs.

All Replies
  • Hi Gaurav,

    The PoC is being calculated and posted by use of Estimate Projects. There is some setup to do and understanding how it exactly works.

    It's too much for a reply like this...

    I fyou have access to training material of AX2012, the training Projects - Advanced handles this topic.

    kind regards,

    André Arnaud de Calavon  |  Microsoft Dynamics AX Solution architect  |  My blog  |  My company

    This post is my own opinion and does not necessarily reflect the opinion or view of my company, Microsoft, both its employees, or other MVPs.

  • Gaurav,

    Andre is correct here. These process involves a lot of setup and various different ways. If you could list your specific requirements, it may help us to answer better.

      Sandeep Chaudhury, Lead Solutions Consultant,SBS Group USA