Julie Johnsey asked a question on 13 Oct 2012 9:36 AM

MRP will not reduce the Sales forecast.  The forecast plan is set to use Sales / Purchase forecast.  MRP Reduction princile is set to  Sales/Purchase forecast.  Negative days vary according to lead time of coverage group.  Set up of master plan is to consider forecast. Forecast plan is set to 365 days.  Does it have something to do with the item coverage group?  The coverage group for this item is set to Requirement - 180 positive - 20 negative.

Any help would be appreciated.

Reply
Tim Schofield responded on 13 Oct 2012 10:45 PM

Have you setup a reduction key and defined this on the coverage group?

Reply
Steven Weaver responded on 14 Oct 2012 12:11 AM

Is there a sales order in the future?

Steve Weaver | Dynamics AX Solution Architect - UK | My Blog

This forum post is my own opinion and does not necessarily reflect the opinion or view of my employer, Microsoft, its employees, or other MVPs.

Reply