BOM Calculation AX 2012 - Explosion Type Multilevel

This question is not answered

Hi,

I have BOM Item A (standard inventory quantity set to '10' units) consuming purchase item B.

Route on Item A says, that it requires 1 hour of set up time (to produce 10 units of item A, set as standard inventory quantity).

Now when I run the BOM calculation for 25 Pcs of  Item - A, with explosion type set to multilevel, I expected 3 Hours of

setup from calculation but actual is one hour only.

Can any one suggest me if i missed something ?

Same was working in AX 2009 but I believe I missed the setting AX 2012. 

Thanks in Advanced.

 

 

 

-Regards

Rahul Shah

All Replies
  • Hello Rahul,

    the setup time is not depending on the quantity you want to produce. Use the run time if working time is depending on quantity produced.

    Regards

    Bodo Vormann

  • Hello Bodo,

    Thanks for your reply but let me clarify that when we do BOM calculation with explosion type set to multilevel (special type which consider setup time on per series basis) standard inventory quantity set up as default order settings will be considered and set up time will be calculated based on per series of standard inventory quantity.

    -Regards

    Rahul Shah