How to solve the Error message "projectAndUserTimeZoneDifferentNotificationText"

Posted on by 30

Hello,

we are having this message everytime when working in the "Project" window.

Do you know how to solve it or what to do, that he didn´t pop up everytime?

Thanks for the support!

pastedimage1618383623691v1.png

Sorry for the German screenshot, but the Message is in English, no worry ;-)

Best regards

Patrick

  • Daniel Bach Profile Picture
    Daniel Bach 40 on at
    RE: How to solve the Error message "projectAndUserTimeZoneDifferentNotificationText"

    Hi Patrick,

    with the installation of Project Operations default Calendar Template is generated.

    Most of the time it uses different Timezone like -12 and do not match with your

    new Setup of Bookable Resources.

    Ensure that the settings are correct:

    1. Verify the Generic Resource Time Zone

    2. Define Workingtime for this Generic Resource using same Timezone

    3. Select Generic Resource in the Gridview and Save calendar as

    4. Set this Calendar in your Parameter Settings as Work hour Template

    5. Apply this Template for all the other Bookable Resources

    Now the Message should be gone.

Helpful resources

Quick Links

Replay now available! Dynamics 365 Community Call (CRM Edition)

Catch up on the first D365 Community Call held on 7/10

Community Spotlight of the Month

Kudos to Saurav Dhyani!

Congratulations to the June Top 10 community leaders!

These stars go above and beyond . . .

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 287,914 Super User

#2
Martin Dráb Profile Picture

Martin Dráb 225,549 Super User

#3
nmaenpaa Profile Picture

nmaenpaa 101,148

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans