Hi Patrick,
with the installation of Project Operations default Calendar Template is generated.
Most of the time it uses different Timezone like -12 and do not match with your
new Setup of Bookable Resources.
Ensure that the settings are correct:
1. Verify the Generic Resource Time Zone
2. Define Workingtime for this Generic Resource using same Timezone
3. Select Generic Resource in the Gridview and Save calendar as
4. Set this Calendar in your Parameter Settings as Work hour Template
5. Apply this Template for all the other Bookable Resources
Now the Message should be gone.