Hi guys,
Hope all is well.
I have a serious issue with an upcoming update.
Here is the story.
Because of a blackout in Microsoft data center the auto scheduled update for 10.0.38 was canceled first in our UAT and afterwards in our Production environment.
Since then, we have deployed multiple customization packages in our UAT environment, and we have also updated the version of the UAT to 10.0.38.
As of now we have 10.0.37 in Production and 10.0.38 in UAT.
As you can understand now if i want to move a release candidate package this will also include the platform version of the UAT because of the image-based deployment.
Here is my problem and the situation in the UAT.
Release 44 deployed in UAT and Prod
PQU of 10.0.37 - deployed in UAT and Prod
Release 48 deployed in UAT, but not in Prod
Service update 10.0.38 deployed in UAT,but not in Prod
PQU if 10.0.38 deployed in UAT,but not in Prod
Release 50 deployed in UAT, but not in Prod.
Now it has been decided that the latest release 50 won't be deployed in production or at least not with all of the change sets that are part of it.
I have paused the 10.0.39 (first wave), but i need to update the production environment with 10.0.38 without bringing any custom code to the production environment.
Is there any way that i can achieve this goal?
Also, is it possible to simply somehow remove the last 2 package deployments from the UAT so we can have an environment that is mirroring the production as it is now except the platform version?
Appreciate your feedback and assistance on this issue.