Hi,
Currently there is a CRM 2011 Application in NA Domain, talking to server level- there are 2 IIS Web servers that host 2 CRM front end APP servers and 2 back end SQL database servers , 2 Asynchronous servers , 2 Reporting servers and 1 Email exchange server. All the servers runs on Microsoft windows 2008 R2 Enterprise OS.
The plan is to migrate the CRM 2011 Application from NA Domain to a restricted zone/domain which needs to raise a firewall in order to access this domain/zone.
Below is the approach for this Migration.
The two IIS web servers will be deployed into new domain/zone leaving the rest servers in the NA domain only. As the OS also upgrades from windows 2008 R2 to windows 2012 R2 , installation of CRM 2011 instance from scratch is performed.
-
- Having DB server in one domain and CRM APP server in another domain is a feasible design?
- In the process of installing CRM 2011 , will be there any connectivity issues with SQL databases which are in another domain?
- The Organization size is close to 3.5 TB, Will be there any issues with deployment manager while importing this Organization unit into installed CRM 2011 instance?
- Once the Migration is done, As SQL databases are in another domain, will be there any plugin triggering issues?
- Finally what kind of issues do i face in this process of CRM Migration?
Appreciate your time for sharing your knowledge!
Regards!
Rajesh
*This post is locked for comments