Hi,
i have created Ressources and give them a cost
but when i create products with bom and with this ressource, they're always at 0 euro
how do i miss ?
best regards
I reup the subject because i think you're right
the cost inside the ressource is on 0
i tell product manager to check and update the price andhave a new look at the product
Have you checked that the unit cost field on the resource is filled in and not only the direct unit cost?
The cost in the BOM is using the unit cost field and not the direct unit cost field.
Hello,
Which Functionality you use. Assembly or Manufacturing?
Regards
Amit Sharma
www.erpconsultors.com