Hi,
i have created Ressources and give them a cost
but when i create products with bom and with this ressource, they're always at 0 euro
how do i miss ?
best regards
Hello,
Which Functionality you use. Assembly or Manufacturing?
Regards
Amit Sharma
www.erpconsultors.com
Have you checked that the unit cost field on the resource is filled in and not only the direct unit cost?
The cost in the BOM is using the unit cost field and not the direct unit cost field.
I reup the subject because i think you're right
the cost inside the ressource is on 0
i tell product manager to check and update the price andhave a new look at the product
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
Congratulations to our community stars!
Expanding mentorship, skilling, and AI innovation
These are the community rock stars!
Stay up to date on forum activity by subscribing.
OussamaSabbouh 796 Super User 2026 Season 2
YUN ZHU 481 Super User 2026 Season 2
AndrewThomas81 377 Super User 2026 Season 2