Hello,
We created a form on CRM , on the form there is start date, end date and duration field.
The duration field is not considering weekends when calculating.
E.g Start Date: Friday 19 Oct 2018 and End Date 22 Oct 2018
Duration: 4 days
But the Duration should be 2 days considering that sat and Sunday are weekend days.
How do I correct this.
Thank you
*This post is locked for comments