Hello,
There are two ways to do this:
-One: Set up your Sales Price list to include the markup and simply use that for your project, and the system will do everything else for you here. This is the preferred way.
-Two: Manually create a new Quote Bid Line: Inside Quote,> Click on Add New Quote Line >; you can add (manually) another Quote Bid Line with a total that is your markup in currency (let’s say your markup comes to $ 9,754, you would need to know this amount to include it in the Quoted Amount field as below):
Option two could be thought of as one-off situations or fixes after the fact.
This might also help: Hack #8: How to use Quotes in Dynamics 365 Project Operations? – part one | Welcome to D365Hacks
Hope this helps. Please, mark this as answered. Thanks.