WBS and resource request workflow in D365 Project Operations Resource/non-stock-based scenarios

Posted on by 25

Hi all, 

we are trying to use the WBS for project planning with the resource request workflow activated in D365 Project Operations Resource/non-stock-based scenarios. For some basic scenarios, the resource request workflow works just fine. Yet, we have a situation when we have WBS tasks (connected as predecessors and successors), fully staffed (there is a hard booked and assigned resource) and we are trying to move forward the date of the first task. According the WBS scheduling logic, all successor tasks move as well. But by publishing the new dates, we get the following message:

pastedimage1645623831622v1.png

Which makes sense due to the fact that the assigned resource has no hard booking for the specific project on the new dates, but the problem is that no resource request is generated. 

Does someone have experience in this, or some guidance of how Microsoft intended this to work?

All help and ideas are welcome

Regards

Irina

Helpful resources

Quick Links

Replay now available! Dynamics 365 Community Call (CRM Edition)

Catch up on the first D365 Community Call held on 7/10

Community Spotlight of the Month

Kudos to Saurav Dhyani!

Congratulations to the June Top 10 community leaders!

These stars go above and beyond . . .

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 287,989 Super User

#2
Martin Dráb Profile Picture

Martin Dráb 225,588 Super User

#3
nmaenpaa Profile Picture

nmaenpaa 101,148

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans