I want to schedule multiple work orders that are related to each other. For example:1. When workorder A is scheduled at 1-12-2021 with endtime at 10:00AM; Workorder B should automaticly scheduled with starttime 10:01AM (doesnt have to be the same resource); Workorder C should be scheduled after workorder B2. Workorder A and B should always start at the same moment3. Workorder A an B should always end at the same timeIs there a way to set the relationship between workorders and does the RSO take the relationship into account? Thanks!
Hi Marcel,
Maybe you can refer following link:
(+) i want to associate my one work order with multiple work order. Is there a way to do this? - Dynamics 365 Field Service Forum Community Forum
Best way to accomplish this is using RSO with this feature - docs.microsoft.com/.../rso-requirement-dependency
Otherwise you will need to build custom logic (flow or plugin) to auto schedule
if this answered your question please mark as verified to help the community!
Thanks Leah Ju! Very helpfull
Thanks Dan! Very helpfull
Hi Partner,
Can you click Yes under "Did this answer your question?" to close this thread if my answer is helpful.
Thanks in advance!:)
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
Congratulations to our community stars!
Expanding mentorship, skilling, and AI innovation
These are the community rock stars!
Stay up to date on forum activity by subscribing.
Travis South 54
11manish 37 Super User 2026 Season 2
ParthPatel249 33