Hi all,
I want to schedule multiple work orders that are related to each other.
For example:
1. When workorder A is scheduled at 1-12-2021 with endtime at 10:00AM; Workorder B should automaticly scheduled with starttime 10:01AM (doesnt have to be the same resource); Workorder C should be scheduled after workorder B
2. Workorder A and B should always start at the same moment
3. Workorder A an B should always end at the same time
Is there a way to set the relationship between workorders and does the RSO take the relationship into account?
Thanks!
Hi Partner,
Can you click Yes under "Did this answer your question?" to close this thread if my answer is helpful.
Thanks in advance!:)
Thanks Dan! Very helpfull
Thanks Leah Ju! Very helpfull
Best way to accomplish this is using RSO with this feature - docs.microsoft.com/.../rso-requirement-dependency
Otherwise you will need to build custom logic (flow or plugin) to auto schedule
if this answered your question please mark as verified to help the community!
Hi Marcel,
Maybe you can refer following link:
Stay up to date on forum activity by subscribing. You can also customize your in-app and email Notification settings across all subscriptions.
André Arnaud de Cal... 291,240 Super User 2024 Season 2
Martin Dráb 230,149 Most Valuable Professional
nmaenpaa 101,156