HI
is there a way is production to have the financial dimensions updated from the ressource instead of the Production itself.
Example
I have a production order with financial dimension
Branch: LAVAL
Department:PRODUCTION
And i have an resources with the financial dimension
BRANCH: JOLIETTE
DEPARTMENT: PRODUCTION
EMPLOYEE: OLIVIER
If i start my production like that , and i create a route card, it will have this financial Dimensions on the line.
BRANCH: LAVAL
DEPARTMENT: PRODUCTION
EMPLOYEE:Olivier
I want that each time i use this ressource, the financial dimensions will stay
BRANCH: JOLIETTE
DEPARTMENT: PRODUCTION
EMPLOYEE: OLIVIER
Thanks for your help
HI Crispin,
Can you tell on what form with what action you get the error? What is the text of the error?
Andre Arnaud de Calavon I tried your recommendation. Unfortunately, according to configuration, an error is thrown when dimension in Production is empty. My Gut feeling is, there should be some way in the application to configure dimensions for Route Operation Priority.
Hi Alzelus,
Did you find a solution to this?
We have a similar situation as well. It appears that the dimensions for Operations "Primary" and "Secondary" are coming from different sources.
"Primary" from corresponding Resource
"Secondary" from Production order.
What we need is, that "Secondary" also takes the dimension from Resource. Probably your same requirement.
Thanks for your answers.
Any way thanks for your help. Was looking for an out of the box solution. will harcode them.
users ...
That what i'm asking people to do bet each end of month i have posting in many branch
If you don't need the financial dimension value coming from the SO, you can delete it on the production order. Then it will merge the value from the resource.
The Laval is coming from the sales order. They generate the production from the sales order, so the production is taking the dim fin of the sales order
Hi Alzelus,
Where does the dimension 'LAVAL' comes from? Is this value required for other production postings?
If the Branch will be empty, then it might default from the resource. If it is already filled, it will not be overridden.
Ok but is there a way for the production module to take the financial dimension from the ressource instead of taking it from the production itself.
André Arnaud de Cal...
292,074
Super User 2025 Season 1
Martin Dráb
230,900
Most Valuable Professional
nmaenpaa
101,156