Suggested answer

Scheduling resources using tasks and teams

Posted on by 15

Hi - We seem to be having some issues scheduling resources using the tasks and team tabs in PO.  Are the two not linked?  We seem to update the dates on one of the tabs and it doesn't update on the other one.

Anyone in the professional services space that has used this functionality we could ask some questions of? 

  • Suggested answer
    Kristina_Skyline Profile Picture
    Kristina_Skyline 90 on at
    RE: Scheduling resources using tasks and teams

    Hi David,

    Try the Task Management solution for Dynamics 365. It gives you the opportunity to assign Tasks to users (can be customized to use Teams), set due dates and priorities and break tasks down into several sub-tasks (also can be assigned to different users).

    Native dashboards in Dynamics 365 provide a simple and convenient way to find, monitor, and manage tasks for the whole team.

    Check it out on AppSource
    https://appsource.microsoft.com/en-us/product/dynamics-365/skyline-consultants-5228552.skyline_taskmanagement?tab=Overview,

    or learn more on the dedicated web-page
    https://skylineconsultants.com/task-management/

    [View:/cfs-file/__key/communityserver-discussions-components-files/803/8103.-User-friendly-Dashboards.mp4:320:240]

  • Tessie Profile Picture
    Tessie 15 on at
    RE: Scheduling resources using tasks and teams

    Hi @daniel bach, I would be interested in a deep dive in these functionalities because we are interested in booking resources per hour and not possible on task but seems possible on Scheduling board but I can't make it work from task/resource generated requirement. And does the resource booking always need to happen from a task requirement or can it be done directly on Scheduling board (because it needs to happen on an exakt time e.g. between 1pm-2pm).

    Kind regards

  • DavidGraham17 Profile Picture
    DavidGraham17 15 on at
    RE: Scheduling resources using tasks and teams

    Hi - Daniel Thanks for the response.  We would be interested to learn more about the integration you mention in your response with URS?  Do you want to reach out to me directly at davidg@kjtgroup.com?    Dave

  • Daniel Bach Profile Picture
    Daniel Bach 40 on at
    RE: Scheduling resources using tasks and teams

    Hi David,

    scheduling is quite different with PO. We have an integration to the URS but Updates, when

    the Project Plan is changed do not apply. e.g. when you "Book" a named Resource to a task

    and then you are shifting the Task.

    There are a lot of use cases and each of them should be checked and added with custom

    logic.

    In this scenario a lot of different entities are involved include PO and default dynamics.

    Sample: Just refer back that a Project Manager will be added to the Project in URS per default.

    I would recommend to review the Requirements and Implement your own custom logic to

    support the URS.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Top 10 leaders for November!

Congratulations to our November super stars!

Tips for Writing Effective Suggested Answers

Best practices for providing successful forum answers ✍️

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,269 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,198 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Product updates

Dynamics 365 release plans