Answered

Service Cost to be added in the Item Cost

(0) ShareShare
ReportReport
Posted on by 10

Hi There, 

We are using AX 2012 R3 and we do have some items that we need to send to a subcon supplier for item modification. 

What module in AX we can use to set it up? 

I will purchase a raw material from Supplier A, I will do PO receiving and I will send the goods to Supplier B. What will be the standard process in AX? 

 

  • André Arnaud de Calavon Profile Picture
    307,856 Super User 2026 Season 2 on at

    Hi Marife,

    Only with some workarounds, you can achieve this requirement. There are various options. This is based on your exact scenario. Can you answer the following questions?

    - Do you want to track sending and receiving the good to and from Supplier B?

    - Are the costs known in upfront or can they vary per order?

    - Is it part of another internal manufacturing process?

  • Marife Vinzon Profile Picture
    10 on at

    Hi Andre,

    Yes, we wanted to track the sending and receiving of goods.

    Ideally what we wanted is to set-up a item number that is for the raw materials and we are going to have a subcon set-up for that item where in we are going to linked it to the subcon supplier + the cost of the services from the subcon, then when we receive the goods from the Subcon supplier, we should be able to receive it under finished good part number.

    Ideal set up:

    Raw Material PN + SubCon Cost = Finish Good PN

    The subcon cost may vary based on customer order, hence it wont be a fixed service cost.

    Thanks again! Hope we can find a work around solution on this so we can eliminate a lot of paper work.

    Thanks!

  • Verified answer
    André Arnaud de Calavon Profile Picture
    307,856 Super User 2026 Season 2 on at

    Hi Marife,

    There is documentation from Microsoft how to achieve subcontracting in Dynamics 365. You can see if the same procedure can be applied in your AX 2012 environment: docs.microsoft.com/.../subcontracting

  • Marife Vinzon Profile Picture
    10 on at

    Hi Andre, 

    Thanks and this is a very good documentation. 

  • Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Good morning Marife,

    If your question has been answered please be so kind and verify it to complete this thread and let also other community users know what helped.

    Many thanks and best regards,

    Ludwig

  • Marife Vinzon Profile Picture
    10 on at

    Hi Ludwig,

    Yes, this answer my requirement. thanks again.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Season of Sharing Community Challenge Winners!

Congratulations to our community stars!

Women in Power Builds Momentum

Expanding mentorship, skilling, and AI innovation

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Martin Dráb Profile Picture

Martin Dráb 536 Most Valuable Professional

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 320 Super User 2026 Season 2

#3
CU-1234529-002 Profile Picture

CU-1234529-002 210

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans