how can we update all assembly orders, sales orders and the MRP/MPS Planning Worksheets to reflect this change?
old structure is :
- item 1:
- item a
- item b (replenishment: assembly)
- nested bom item 1
- nested bom item 2
- item d
current structure is :
- item 1:
- item a
- item b (replenishment: assembly)
- nested bom item 1
- nested bom item 2
- item c (replenishment: assembly)
- nested bom item 3
- nested bom item 4
- item d
- sales order is for item 1
- MPS creates assembly order for item b (what would be expected: orders for b and c)
- MRP creates only purchase suggestions for nested bom item 1, nested bom item 2, (what would be expected: also for nested bom item 3, nested bom item 4)
we have tried this: docs.microsoft.com/.../production-how-to-replan-refresh-production-orders
but it seems not to be working for assembly?
could it be that BC only solves one nested assembly item, and the updtaing is not the problem here?
just checked - also NEW sales orders do not include all sub-assemblies in MPS/MRP Planning Worksheets.
------
EDIT:
i have created new dummy items reflecting this exact structure, and the MRP/MPS Planning Worksheets runs fine with them. so i think there's somehow an issue with the real world data.
whether i run the MPS/MRP Planning Worksheets suggestions with "stop and show first error" the result is the same - no errors shown.
how can i debug this? is there a Planning Worksheets log that i can scan through and see why some BOM items are not considered?