Hi All,

we have imported pending costs related to a service item with Use cost price by variant active 

When activated, the field Price in the Manage Costs fasttab is populated with the first price imported.

Anyone know how to avoid this behavior?

Costing version setup below

BLOCKING POLICIES
Block changes No
Block activation No
MODEL
Costing type Standard cost
VERSION VALUES
Recording restriction Yes
Incl. in unit price Yes
Round off No
ALLOW PRICE TYPE
Purchase price No
Cost price Yes
Sales price No
I have the same question (0)
  • Zuk Profile Picture
    65 on at

    With this price in the record entry the system calculates the BOM price of items with this service with the price in the Manage Costs Fast tab and not using the related cost in the Active costs related to the costing version

  • Suggested answer
    Charlotte X Profile Picture
    on at

    Hi FabioC,

    If you're using an actual costing method, I think the system will use the 'Price' on the 'Manage costs' fast tab if it does not have enough information to be able to calculate a cost price for an inventory issue.

  • Zuk Profile Picture
    65 on at

    Hi Charlotte,

    we are using Standard cost. I get your point on inventory issue and I agree with you on that.

    What it is strange is the behavior during BOM calculation where the service item is used.

    Example:

    BOM for ITEM A includes Configuration A of the service A with price 10€

    BOM for ITEM B includes Configuration B of the service A with price 8€

    We have imported pending prices and then activated them for SERVICE A for all configurations as follow

    Configuration C 5€

    Configuration B 8€

    Configuration A 10€

    The manage costs fast tab in the entry for Service A Price field is updated with the price 5€ (Configuration C cost)

    During the BOM calculation the price used for ITEM A and also for ITEM B is 5€ and not the excpected 10 and 8.

    Best regards.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Congratulations to our 2025 Community Spotlights

Thanks to all of our 2025 Community Spotlight stars!

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 605 Super User 2025 Season 2

#2
Abhilash Warrier Profile Picture

Abhilash Warrier 437 Super User 2025 Season 2

#3
Martin Dráb Profile Picture

Martin Dráb 348 Most Valuable Professional

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans