All of our Agreement Invoice Dates have the Postpone Generation Until field set to 1/1/1900 12:00 AM.
Is this expected behaviour? Or should they have the date the invoice is going to be generated?
We are using Field Services version 8.8.22.57

All of our Agreement Invoice Dates have the Postpone Generation Until field set to 1/1/1900 12:00 AM.
Is this expected behaviour? Or should they have the date the invoice is going to be generated?
We are using Field Services version 8.8.22.57
Hello,
When I looked at the audit history of one of my agreement invoice dates I noticed that the Postpone Generation Until field was first set to 1/1/1900 when the record was created. The date was updated one week before the actual invoice date. If you open the field settings record (FS app, Settings>Field Service Settings>Agreements) you can configure how far in advance you want to generate invoice dates, agreement invoices etc. More details here: docs.microsoft.com/.../configure-default-settings
Please mark this answer as verified if helpful.