Hello
Not sure about your status here and what did you post already or not.
If issue is that production order started but done with for example a Work center that gets unit cost 3 and it should be 2....
Then what you could test:... not an easy process steps, so test this carefully before to do it in prod....
Go to your production order and open the routing.
Then at production journal level, you can reverse the previous entry by adding negative time (negative run time for example if it was the one posted)
Check your work center card to see if specific cost is allowed or not.
If allowed, we can change it manually at production order routing level
If not, then we need to change it at Wok center card level
Then go to your routing line and here you will be able to add 1 additional routing line
and add field unit cost: as shared if specific unit cost is allowed we can change it manually to unit cost 2
(if not allowed, then we can add what we want BUT system will use unit cost from Work center card when posting!)
Go to production journal and post this added routing line with needed time allocated (0 qty)
Not sure if you see what I mean but it could help you to work around that.