Hello,
We are an engineering and fabrication company that delivers complete turn-key systems. In the job planning line, is it possible to setup a "materials" budget under which items a,b,c,d,e, etc will be ordered via a purchase order and have that "materials" budget job planning line be the budget that the components are billed against?
The best I can see thus far is that each item that needs to be ordered needs to have it's own job planning line of which we are can hundreds of components or items that in this manner would need their own planning line.
Same question for resources, can we setup a generic resource "Electrical Engineer" for example, and have any one of the electrical engineers bill against and draw upon the "Electrical Engineer" budget? In this case, only if the individual engineer is entered into the job planning line does it record properly else it just adds it to the budget.
Doesn't appear in Financials that the "usage" can be unlinked.
Thank you in advance.

Report
All responses (
Answers (