Microsoft Dynamics NAV forum
Suggested answer

Resource used in job

Posted on by 115

Hello,

When a timesheet based resource is allocated to a job, this cost never hits the G/l. How does it get calculated in wip? I have allocated some hours using timesheet and ran a job journal to pick up the costs. When I run wip I get warnings with the column g/l cost not allocated to g/l showing the resource cost.

Should I ignore it ?

Categories:
  • Suggested answer
    azelaya59 Profile Picture
    azelaya59 2,807 on at
    RE: Resource used in job

    Look at this link:

    docs.microsoft.com/.../projects-setup-projects

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Anton Venter – Community Spotlight

Kudos to our October Community Star of the month!

Announcing Our 2024 Season 2 Super Users!

A new season of Super Users has arrived, and we are so grateful for the daily…

Dynamics 365 Community Newsletter - September 2024

Check out the latest community news

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 290,552 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 228,552 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,148

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans