Hi,
When Automatic Cost Adjustment is set to Day, Business Central runs the cost adjustment once per day (usually during posting or batch jobs) likewise When we Set “Always” System auto adjustments are applied instantly whenever you post a transaction, ensuring costs are always up to date.
Example:
You buy an item at $100 and later another batch at $120.
You sell one unit right after the second purchase.
If set to Always:
- The system immediately recalculates and applies the correct average cost, so your sale reflects the updated $110 average.
If set to Day:
- The sale may temporarily use the old cost (e.g., $100).
- Later, during the daily adjustment, the system updates the cost to $110 and posts an adjustment entry.
You can track or verify the Automatic Cost Adjustment in Business Central when it’s set to Day from below Pages:
1. Item Ledger Entries
2. Value Entries
3. Inventory Valuation Report or Cost Adjustment Report.
When it Run ?
The exact timing depends on your environment’s scheduled jobs or when transactions are posted.
Typically, adjustments are triggered at the end of the day or the next posting run, not instantly after each transaction.
Hope it will help you.
Please Verify if you found the answer helpful so that it will help others.
Many Thanks
Aman