Batch job in priority based in D365FO

(2) ShareShare
ReportReport
Posted on by 712
Hi team,
 
I have created a custom batch job. I like to prioritise this batch job. Is it possible?
 
Pls advise, thanks 
Categories:
I have the same question (0)
  • Verified answer
    Martin Dráb Profile Picture
    240,280 Most Valuable Professional on at
    If you put the title of your thread to a search engine, you'll easily find the documentation page: Priority-based batch scheduling
  • CU10121822-0 Profile Picture
    712 on at
    Yeah Martin, I have already do research on this.
     
    But confusing on how it's worked in real world. That I forgot to mentioned here.
     
    I am looking for an example on real world to understand the concept.
     
    Pls advise, thanks
  • Martin Dráb Profile Picture
    240,280 Most Valuable Professional on at
    Could you please elaborate which part you don't understand and what you'd like to demonstrate by an example? Trying to rephrase the whole documentation and giving you a random example of some aspect doesn't sound efficient. Please be more specific about what you actually need.
  • CU10121822-0 Profile Picture
    712 on at
    What I understood, to get this feature we should enable "batch scheduling," in Feature management. 
     
    Once we got this, I saw we have an option for scheduling priorities like 
     
    Low
    High
    Normal
    Reserved 
     
    My question is here, how this priorities will work in real world. If I set to high or  reserved.
     
    Pls advise, thanks!
  • Suggested answer
    Syed Haris Shah Profile Picture
    1,821 Super User 2026 Season 2 on at
    Hi @CU10121822-0,

    To understand the value of Priority-based Batch Scheduling, the following explanation should help clarify how it works in practice. Priority based scheduling (PBS)  improves how batch jobs are distributed across AOS batch servers.
     
    Previously, batch groups had to be assigned to specific batch servers, which could result in one server being overloaded while others remained idle. With PBS, batch jobs are scheduled based on their priority rather than a fixed server assignment.
     
    For example, if one server is busy processing a large number of MRP jobs while another server is available, the available server can pick up other high-priority batch jobs instead of waiting for a specific server. This provides better resource utilization, improves batch throughput, and ensures that critical business processes such as invoice posting, payments, or inventory close are processed more efficiently.
     
    Regards,
    Syed Haris Shah
  • CU10121822-0 Profile Picture
    712 on at
    Thanks Syed,  not fully understood. Could you please elaborate more in details. And what is PBS?
     
    Pls advise, thanks 
  • Suggested answer
    Subra Profile Picture
    1,938 Super User 2026 Season 2 on at
    Hi @CU10121822-0

    I hope Batch will not check the Priority alone while executing the batch jobs. It will check the batch scheduled time and status (Waiting) and look for the available threads as well.
     
    Thanks,
    Subra

    If this helped, please mark it as "Verified" for others facing the same issue
  • Verified answer
    Martin Dráb Profile Picture
    240,280 Most Valuable Professional on at
    Okay, so you want to know how this priorities will work in real world and you want a concrete example. It's already covered in the documentation, so let me simply quote it:
     
    For example, suppose there are 100 batch tasks for processing. Forty tasks come from the reserved queue, 30 from the critical queue, 15 from the high queue, 10 from the normal queue, and five from the low queue. The system doesn't select the priority-based order of execution for processing. Instead, it uses the weight of the batch tasks from each priority.
     
    Priority     Weight
    Low     5%
    Normal     5%
    High     15%
    Critical     30%
    Reserved capacity 40% + Dedicated X threads
     
    As you see, it doesn't mean that the system will process all tasks of the highest priority before taking any other. Instead, it tries to schedule tasks of all priorities, but it'll give a higher weight to those with higher priorities when assigning tasks. In the example above, you'll still get forty tasks (not all one hundred) with the highest priority and five tasks (5%) with the lowest priority.
     
    By the way, it's not true that distribution over multiple batch servers wasn't possible before. A batch group can be associated with multiple batch servers, not just one, and then all those servers process jobs for the given batch group.
  • André Arnaud de Calavon Profile Picture
    306,672 Super User 2026 Season 2 on at
    Hi,
     
    I think the last reply from Martin should help you. I addition, configuring all batch jobs and tag them for a specific priority requires some overthinking. The recurrence and at what time of the day is an important factor to take into consideration as well. E.g. having 1000 batch jobs running with a recurrence of 1 minute is not recommended. 
  • Syed Haris Shah Profile Picture
    1,821 Super User 2026 Season 2 on at
     
    PBS stands for Priority-Based Scheduling (PBS).

    I'm glad @Martin Dráb was able to provide a great explanation along with a helpful example to answer your question. Thanks for the clarification!
     
    Regards,
    Syed Haris Shah

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Season of Sharing Community Challenge Winners!

Congratulations to our community stars!

Women in Power Builds Momentum

Expanding mentorship, skilling, and AI innovation

Congratulations to the July Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Martin Dráb Profile Picture

Martin Dráb 265 Most Valuable Professional

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 261 Super User 2026 Season 2

#3
Subra Profile Picture

Subra 229 Super User 2026 Season 2

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans