Is there a way to be able to see if there is the ability to fulfil a production order based on current work centre load without creating the production order as planned/firm planned?
For example, if I create a new Production BOM which contains lots of other top level parts (each of which requires production), is there a way to input a due date and see whether there is the ability to fulfil that based on work centre availability?
What I don't want to have to do is create loads of production orders for all levels just to check if the availability to fulfil it is there, and then have to delete them all afterwards if there isn't capacity.
I was hoping a simulated production order would do the job but it appears that all this does is calculate costs.