Vendor Delays in Master planning

(0) ShareShare
ReportReport
Posted on by 5

We've setup purchase lead times for each item in the default order settings (e.g. 25 working days), but due to COVID a lot of our vendors are experiencing delays. They don't really give us a bigger lead time, but quite often, they will just give us a much later date than what master planning had calculated based on that lead-time.  Because the default purchase lead-time is still 25 days, master planning will just create a new planned purchase order, 25 days from now so it can fulfill all the sales orders.When we are using CTP calculations, our calculated delivery days will be based on that planned purchase order. 

So I'm looking for a solution to block the creation of new planned purchase orders before the date the vendor has promised (without changing the purchase lead time).

extra info:

Vendor calendars isn't an option because all the items of that vendor would be impacted

We don't use trade agreements.

thanks for your input!

  • Suggested answer
    Jack Moran Profile Picture
    Jack Moran 85 on at
    RE: Vendor Delays in Master planning

    Agree with Andre that setting Safety Margins under Coverage Groups is one possibility. It will allow you to address multiple items with one change IF the items that need to have their leadtime offsets altered will align well within a given Coverage Group. Another possibility is the leadtime override tab on the Item Coverage settings themselves which would be specific for a given item. That said, I'm not a big fan of either as it puts multiple variables into the equation when the system is calculating leadtime offsets for planning. Makes things more confusing when analyzing planning outputs. If your using Item Templates, there may be a third option to explore there, but Item Templates have a history of being finicky to work with.

  • André Arnaud de Calavon Profile Picture
    André Arnaud de Cal... 292,162 Super User 2025 Season 1 on at
    RE: Vendor Delays in Master planning

    Hi Janssens Jan,

    On the master plan, there is a setting called 'Receipt margin added to requirement date'. This would be added to the lead time.

  • RE: Vendor Delays in Master planning

    Hi Janssen Jan,

    I don't think we have out-of-box functionality to support this.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Announcing Our 2025 Season 1 Super Users!

A new season of Super Users has arrived, and we are so grateful for the daily…

Vahid Ghafarpour – Community Spotlight

We are excited to recognize Vahid Ghafarpour as our February 2025 Community…

Congratulations to the January Top 10 leaders!

Check out the January community rock stars...

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 292,162 Super User 2025 Season 1

#2
Martin Dráb Profile Picture

Martin Dráb 230,962 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Product updates

Dynamics 365 release plans