Hi Kaydee,
Thank you for the explanation of your situation. I'm going to attempt to restate your questions and then answer them.
1. "You are avoiding using the Job Planning Lines defined as Budget because they do not show on the Job Quote or in the Billable Price values displayed in the Job Statistics. Is it possible to use a different report which would include the Budget Job Planning Lines in the Job Quote?"
This is expected functionality in that only Billable or Both Job Planning Lines are included in the Job Quote. Similarly, only the Billable or Both Job Planning Lines will later be included in the Invoice for the Job.
2. "We have found that if we create the job planning line as 'both billable and budget', the time is recorded and the qty remaining is updated appropriately, however the qty to transfer to invoice does not update with only the time entry amount. We can do the math, but this seems to be a flaw, as we would essentially want to run the job to pull all time card postings to jobs for invoicing. Instead, we have to go through each line, look at qty remaining and back out the qty already invoiced to appropriately get the value to transfer. "
There is not a method or job to recalculate the Qty. To Transfer to Invoice field. It is expected that this filed is manually adjusted, as needed.
3. "Furthermore, the edit in excel button is available but it doesn't allow for publishing changes. If this was available, it would help make the process to 'do the math' for the qty to transfer to invoice much more simple."
Are you attempting to use the Edit in Excel button in the Job Planning Lines page? Are you encountering an error?