Planning Optimisation with Finite Capacity and multi-level BOM's

(0) ShareShare
ReportReport
Posted on by 2

I am working on an implementation where we have significant variations in demand, and resources are regularly over capacity in an environment of multi-level BOM productions.

We are running repeated Master Planning (planning optimisation) as regeneration within minutes of each other, and seeing different outputs where dates and quantities of the planned works orders are changing.

Master planning is being run consecutively within minutes, with no configuration or data changes, and no planned orders being firmed, approved or deleted, the planning runs are being executed within the same hour of system clock, so it cannot be the initial start time of the available capacity.

All resources are using the same working times calendar, all route operations are pointing to specific resources and not resource groups. Finite capacity timefence is 2 months.

All master plan ‘calculated days’ are unticked.

The only variable we are not able to control is how planning optimisation evaluates competing requirements for the limited capacity.

Has anyone experienced such scenarios previously, and could suggest some solutions to get consistent outputs from planning optimisation when using finite capacity?

  • Laurens vd Tang Profile Picture
    5,292 Super User 2026 Season 2 on at

    Hi @AndeC ,

     

    Do you mean that you see different outputs when the dates and quantities are changed?

     

    Best regards,

    Laurens van der Tang

  • AndeC Profile Picture
    2 on at

    Hi @Laurens vd Tang Thank you for your interest.

    Yes, my demand dates and quantities have not changed, my PO's have not changed… no data has changed.

    Running full Master planning regeneration within minutes of each other produces different planned order outputs in dates and quantities for production and purchases.

    We are using multi-level BOM's with finite capacity on resources. It appears that planning optimisation does not sequence its consideration of competing equal demand on finite resources. Where equal demand appears to only be considering the required date (not quantities or any firmed/approved orders that supply the production demand).

    Thus, for example, where ItemA and ItemB both demand capacity on the same finite resource for availability on the same date (and time if job scheduling) → 1st master planning run will assign ItemA to the available capacity and delay ItemB. 2nd run it will assign ItemB to the available capacity and delay ItemA.

    With changes in dates of the planned production, coupled with item coverage method of period seven days, this extrapolates up the BOM hierarchy to produce planned availability of finished goods in different quantities and different dates.

    via MSFT support ticket it has been diagnosed that planning optimisation does not produce a deterministic output when used with finite capacity, and a solution is being reviewed for future updates.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Season of Sharing Community Challenge Winners!

Congratulations to our community stars!

Women in Power Builds Momentum

Expanding mentorship, skilling, and AI innovation

Leaderboard > Supply chain | Supply Chain Management, Commerce

#1
Laurens vd Tang Profile Picture

Laurens vd Tang 75 Super User 2026 Season 2

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 74 Super User 2026 Season 2

#3
Patrick Mouwen Profile Picture

Patrick Mouwen 35

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans