I am working on an implementation where we have significant variations in demand, and resources are regularly over capacity in an environment of multi-level BOM productions.
We are running repeated Master Planning (planning optimisation) as regeneration within minutes of each other, and seeing different outputs where dates and quantities of the planned works orders are changing.
Master planning is being run consecutively within minutes, with no configuration or data changes, and no planned orders being firmed, approved or deleted, the planning runs are being executed within the same hour of system clock, so it cannot be the initial start time of the available capacity.
All resources are using the same working times calendar, all route operations are pointing to specific resources and not resource groups. Finite capacity timefence is 2 months.
All master plan ‘calculated days’ are unticked.
The only variable we are not able to control is how planning optimisation evaluates competing requirements for the limited capacity.
Has anyone experienced such scenarios previously, and could suggest some solutions to get consistent outputs from planning optimisation when using finite capacity?