How o calculate WIP for Jobs in NAV2009. I prefere classic client.
*This post is locked for comments
How o calculate WIP for Jobs in NAV2009. I prefere classic client.
*This post is locked for comments
You need to choose WIP method on job card in option field WIP Method (Cost Value,Sales Value,Cost of Sales,Percentage of Completion,Completed Contract). You can find in help of this field detaile about configure it.
If you have posting entries, you need to start WIP->Calculate WIP and system will make Job WIP entries. After that you need to start function Job Post WIP to G/L for this job.