Answered

Production control error Picking not Acknowledge Fianancial

(0) ShareShare
ReportReport
Posted on by 20

I have one production oder that end user Reciept report as finish but forget  check  "Report as finish" ( in picture).

I was update status for this production order to END . Result material in "Picking list " not  Acknowledge Fianancial date and voucher in General journal entry.

mpo.PNG

I have the same question (0)
  • Suggested answer
    Christoph Thaler Profile Picture
    5,442 on at
    RE: Production control error Picking not Acknowledge Fianancial

    Hi Crisdu,

    Unfortunately your Problemisolierung not 100% clear to me. Is it correct that the status of the production order is „ended“ and now you want to change / add something? If it is like this, this is not possible because ending a production order leads to a situation where you cannot post additional journals to the production order. If not please describe your problem in more details.

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at
    RE: Production control error Picking not Acknowledge Fianancial

    Good Morning Crisdu,

    I see.

    Is your ending production voucher then incomplete or does it contain to much/less costs?

    What do you try to do?

    Would be great if you could elaborate.

    Many thanks and best regards,

    Ludwig

  • Crisdu Profile Picture
    20 on at
    RE: Production control error Picking not Acknowledge Fianancial

    Thanks bro! I want repost picking list material to acknowledge "financial info" but my production order was End.

  • Crisdu Profile Picture
    20 on at
    RE: Production control error Picking not Acknowledge Fianancial

    Thanks bro! I want repost picking list material to acknowledge "financial info" but my production order was End.

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at
    RE: Production control error Picking not Acknowledge Fianancial

    Hi Crisdu,

    I see.

    So, your production costs are too low then because the material was never picked and consumed / used?

    Is that right?

    What kind of valuation model do you use?

    Do you use a current costing model (fifo, lifo, etc.) or do you use standard costing for your production items?

    Best regards,

    Ludwig

  • Crisdu Profile Picture
    20 on at
    RE: Production control error Picking not Acknowledge Fianancial

    Hi Ludwig,

    So, your production costs are too low then because the material was never picked and consumed / used?

    - YES, my production Costs will not exact.

    And my material  have status is deduct , how can i change status to Sold and System auto adjust finance?

    I use FiFo for my item. And use avegrate cost. Not use standard cost.

    Best regards,

  • Verified answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at
    RE: Production control error Picking not Acknowledge Fianancial

    Good Morning Crisdu,

    If the production is ended then there is not much that you can do with this production order.

    However, to get the inventory value corrected for the produced item, you can record an adjustment of the item transaction in the inventory and close form in the inventory module.

    This will fix the pricing/cost issue of your finished items.

    At the same time, you still do have too much materials - the ones that have been picked - in your inventory. You would also need to adjust this for example by posting an inventory adjustment journal. Otherwise, your stock levels are too high if the items have been consumed during production.

    Overall, making the necessary corrections is all a bit cumbersome and manual and I would recommend that you test them carefully in a demo/test environment first.

    Best regards,

    Ludwig

  • Crisdu Profile Picture
    20 on at
    RE: Production control error Picking not Acknowledge Fianancial

    Thanks Ludwig!

    But how to balance quantity between  of physical and finance ?

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Martin Dráb Profile Picture

Martin Dráb 683 Most Valuable Professional

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 563 Super User 2025 Season 2

#3
Sohaib Cheema Profile Picture

Sohaib Cheema 398 User Group Leader

Last 30 days Overall leaderboard