Hi,
Is it possible update or revaluate Unit Cost value recorded in Job Ledger Entries?
We want to record actual resource cost in Job. But resource actual costs are calculated at month end.
The projects are proceeding, and so once temporary resource costs are posted in Job Journal for each Job.
The actual monthly resource unit costs are calculated at the month end.
What we want to do is the old Resource unit costs are reversed and the new costs are posted in Job Journal at the same time.
Is there a page or functionality like Item Revaluation Journal for Job Journal in Business Central?