Can anyone confirm if there is a way to close a project task tagged as a milestone so it doesn't get flagged as an overdue project task.?
Can anyone confirm if there is a way to close a project task tagged as a milestone so it doesn't get flagged as an overdue project task.?
Hi DanKalion,
My answer is for Project Operations, Lite and Non-Stocked deployments:
If I understand your question well, the only way is to mark that task as complete that task (and its child tasks as well), otherwise it will trigger the overdue inside the Task tab.
I am curious to understand how that is causing you a problem?
Please, mark this as answered if it is the case.
Thank you,
Juan Simon