Hello Ezra,
There are a few different ways that you can accomplish this in Dynamics 365 Financials using the Jobs area which is available using the Suite experience. These options do all require some sort manual calculation to break up the percentage.
I'm going to illustrate these options using the following very simple example: You have a Constructions Job that requires the installation of 10 shelves (which are in your inventory) that each have a price of $100 to install, so the totally would be $1,000 to install the shelves.
1. You create a Job for this shelf installation.
2. Add a Task to this Job for the shelf installation.
3. In the Job Task you then create the planning line(s) for your Items and Resources. There are different ways you could set this up and it will affect how you do the billing. In my options I'm only going to list out the options for the item, but the options would be similar for a planning line that is a resource. Here are the options that could work:
Option 1
- Create 1 Budget and Billing Planning line for the 10 Shelves and when you are ready to bill 80% edit the Qty to Transfer to Invoice to 8 so that 80% of the quantity and price would be invoiced.
- You would later then invoice the remaining 2 quantities on the line to complete the billing.
Option 2
- Create 3 Planning lines for the Shelves.
--One Budget Planning Line for the Shelves with 10 Quantity which you would then post to the job journal to deplete the quantities.
--One Billable Planning Line for the Shelves Item with 8 Quantity or 10 Quantity with 80% of the Unit Price($80) which you would use to then Create an Invoice which would be $800 (80% of the total).
--One Billable Planning Line for the Shelves Item with 2 Quantity or 10 Quantity with 20% of the Unit Price($20) which you would use to then Create an Invoice which would be $200 (20% of the total).
Option 3
- Create 3 Planning lines for the Shelves.
--One Budget Planning Line for the Shelves with 10 Quantity which you would then post to the job journal to deplete the quantities.
--One Billable Planning Line for a G/L Account with Quantity of 1 a Unit Price of $800 which you would then Create an Invoice for $800(80%), however, you would not see the line item on the sales invoice.
--One Billable Planning Line for a G/L Account with Quantity of 1 a Unit Price of $200 which you would then Create an Invoice for $200(20%), however, you would not see the line item on the sales invoice.
4. Lastly, you have the Job Actual to Budget that can likely give you what's remaining to be billed. The option that you select to work with above will likely change how and what prints on this report.
These options may or may not work for your exact scenario and it should likely be tested to make sure it will work for what you need. For example, is it feasible to manually calculate out 80% of the quantity? Dynamics 365 for Financials Jobs are typically geared toward Time and Materials, but there could be some extensions that become available later that offer something a little different than these options.