Purchase order - modify quantity ordered on PO already released in GP

Question Status

Unanswered
BMC asked a question on 8 Sep 2017 12:13 PM

How do you modify quantity ordered in Microsoft GP?  The PO is already released and sent to the supplier

Reply
Leslie Vail responded on 13 Sep 2017 5:31 PM

Hi,

As far as GP is concerned, you can just bring up the PO and change the quantity. The PO will take on the status as Change Order, and I suppose you would want to reprint the PO and send it to your supplier.

What is your specific question? Does it have to do with printing a new PO with the change highlighted?

Kind regards,

Leslie