Applies to Product - Dynamics 365 Supply Chain Management
What’s happening?
Production order rescheduling is impacted by the configuration of the phantom item operation route group, leading to unexpected delivery dates for sub-production items.
Reason:
The phantom level utilizes a route group that avoids scheduling and costing configuration. This results in different behaviors during the rescheduling of production orders, particularly when the phantom item route group is set up in a specific manner.
Resolution:
- Navigate to Production control | Setup | Routes | Route groups and create a new route group.
- Unmark all options in the setup area and save the record.
- Create the raw material and sub-assembly products, ensuring they are set up correctly in the system.
- Create the phantom item and ensure it is configured with the appropriate BOM and route settings.
- When scheduling production orders, ensure the scheduling direction is set correctly (e.g., Backward from scheduling date).
- Review the delivery dates on the production orders for the affected items to ensure they align with the expected outcomes.
- If discrepancies occur, verify the route group settings and the scheduling configurations to ensure they are correctly applied.