Applies to Product -Dynamics 365 Project Operations
What’s happening?
There is an error in duration calculation from the start date to the end date of a task in the WBS tab in D365 Project Operations.
Reason:
Possible causes include:
- The duration and start/finish dates can appear out of sync due to discrepancies in working hours between the project calendar and the resource calendar.
- The project calendar may have different working hours than those set in the resource calendar, leading to incorrect duration calculations.
- Ensure that the working hours in the project calendar and the resource calendar are consistent.
- If discrepancies in working hours are found, update the working hours accordingly and verify the calculations again.
- Adjust the settings for Project task time tracking and Project actual value tracking to "Real-time update."