Applies to Product – Dynamics 365 Project Operations
What’s happening?
Customers are inquiring about how to allocate resources as part-time in Project Operations, specifically how to indicate that a resource has 50% availability on a project and manage part-time resources in terms of scheduling and hour counting.
Reason:
This arises from the need to effectively manage part-time resource scheduling and tracking hours within Project Operations.
Resolution:
To allocate a resource as part-time and indicate 50% availability, follow these steps:
1. Navigate to Projects in Project Operations, then select the project you would like to modify.
2. Select the Team tab, then click New from the sub-grid.
3. When populating the team member information, set Allocation Method to "Percentage Capacity."
4. Enter the Percentage as 50%.
5. Select Save and Close