Primary Secondary operation priority and run time in production route scheduling
Views (936)
Primary Secondary operation priority and run time in production route scheduling
-------------------------------------------------------------------------------------------------------------------------
Priority is used to control operations that occur at the same time, and that appropriate one or more operations resources at the same time.
The priority determines which operation is the primary one.
The primary operation should be the operation loading the operations resource that is regarded as the bottleneck for simultaneous operations.
A bottleneck operations resource is not defined in any special way in the system, because individual routes and productions determine which operations resources page the bottleneck.
If the operation is not primary, the times from the primary operation are used to schedule the secondary operation.
This means that the times do not have to be specified for secondary operations.
If there are no parallel operations for an operation number, the operation should be created as a primary operation
While in route one can specify the times on secondary operations but D365FO would take the time only for primary operation.
This is seen in production route when you try to edit the secondary operations, the 'times' fields are all disabled.