Hi everyone,
I’m a total newbie to D365 MRP and running into a planning challenge in D365 Supply Chain Management related to paired production items (TX and RX).
In our setup, a finished product requires one TX and one RX module, and both modules must go through a Burn-In test together.
The Burn-In chamber needs one TX + one RX at exactly the same time, otherwise the test cannot run.
Here’s the problem:
- Both TX and RX appear as separate components in the parent BOM
- MRP plans them independently, based on their individual lead times and coverage settings
- Even when they are required by the same parent, the planned production orders do not align
- We end up with TX ready earlier and RX later (or vice-versa), blocking the Burn-In process
What I need:
A way for MRP to force TX and RX to be planned with the same requirement date, so they:
- get planned together
- get firmed together
- are available at the same time
- arrive as a matched pair for the Burn-In chamber