Cleaning time after production

(4) ShareShare
ReportReport
Posted on by 38
Dear community,

After our production orders, we need time to clean the equipment. From costing perspective, this is considerable.
Of course, we have setup time and run time.
This cleaning time is very similar to setup time so i am considering to use setup time for this. (Posting to the same ledger account as setup time is ok)
But it's not exactly the same as it is after the run time, not before.
If i am missing an option in standard F&O which is exactly for this, I would like to know. Otherwise we will use the setup time for this.
 
I have the same question (0)
  • Suggested answer
    Rajjos Profile Picture
    85 on at
    Hi Janco,
     
    Consider this setup on the route. You need to experiment with this and verify whether the system is taking into account the time for cleaning and posting to the ledgers.
     
     
     
    Hope this helps!!
     
    Rajashree
     
  • Laurens vd Tang Profile Picture
    4,394 Super User 2026 Season 1 on at
    Hi Janco,
     
    Is the cleaning time different per production order?
     
    Best regards,
    Laurens van der Tang
  • Janco van Dijk Profile Picture
    38 on at
    Hi Laurens,

    Yes, cleaning time differ's and we need to keep track of actual costs.

    Regards,
    Janco
     
  • Laurens vd Tang Profile Picture
    4,394 Super User 2026 Season 1 on at
    Hi Janco,
     
    Thanks for the clarification. Is the cleaning always after the last operation?
     
    Best regards,
    Laurens van der Tang
  • Drew Lencsak Profile Picture
    433 on at
    Do you only want to track the cost in aggregate or per production order? I have several clients who will create a dummy item for cleaning runs and schedule the clean times as their own orders to control them a bit more. Of course, this option only works if you are okay not having that cost linked to the production order the cleaning run was related to. You could try making the cleaning run a pegged supply order with unique run times but that would treat it like a sub assembly that was needing to be consumed before your actual production order is finished. Was just a curious thought on the costing piece. Good luck!

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Congratulations to our 2025 Community Spotlights

Thanks to all of our 2025 Community Spotlight stars!

Leaderboard > Supply chain | Supply Chain Management, Commerce

#1
Mallesh Deshapaga Profile Picture

Mallesh Deshapaga 1,093

#2
Laurens vd Tang Profile Picture

Laurens vd Tang 193 Super User 2026 Season 1

#3
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 148 Super User 2026 Season 1

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans