Hello everyone,
I am facing an issue with Planning Optimization in D365 Finance and Operations related to the BOM/formula multi-level explosion.
I am using a formula that contains only raw materials (no semi-finished items, no co-products, no by-products, no phantom items).
All coverage settings, BOM versions, site validation, and formula activation have been verified.
However, I am experiencing the following behavior:
-
When I run Planning Optimization, the system creates a planned order for the finished good, but does not explode the lower levels of the formula (level 1 and level
-
When I open production order for the finished good and perform a manual explosion (Calculate), the system correctly generates the purchase requirements for all raw materials.
So the manual explosion works correctly, but Planning Optimization does not perform the multi-level explosion automatically during the master planning run.
Has anyone encountered this issue?
Is this a known limitation, a missing configuration, or related to Planning Optimization behavior with multi-level formulas?
Any guidance or confirmation from the community would be very helpful.