Hello Everyone,
Appreciate your help!
In the Gantt chart, Operation 30 requires 10 hours of processing time. However, the system is assigning only one resource from the capability and scheduling it according to a single day shift, instead of splitting the operation across two resources. As a result, the operation appears to take longer than it actually does in practice.
On the ground, once one resource’s shift ends, another resource takes over. Shouldn’t the system split the operation between two resources?
I would appreciate if someone can help or share suggestions on how to resolve this issue.