Hi all
I have parallel operations for my productions. I have a welding operation and a paint operation. I can start the paint operation before the welding operation is finished. I have tried with Transport time and Queue after, but the result say I can start the operations at the same time. I want the paint job to start a bit later than the welding operation. How can I setup this?
Thanks in advance