Hi community,
masterplanning uses the requested or confirmed shipping date for calculation. If there is a confirmed date, mrp will use the confirmed date. If not, dynamics will use the requested date.
New sales order lines are usually unconfirmed, so does only have a requested date when calculation a possible delivery date using CTP or batch-CTP (new planning optimization for batch-ctp).
This means, that new sales order lines that are early calculate a possible confirmed delivery date, but already existing and confirmed lines get a delay. We cannot believe that this is true and that there is no solution.
There should be a parameter where you can decide to prefer confirmed dates over requested dates.It would be great if it were possible to define a period in which confirmed lines win over requested lines.
Does anybody have a solution for this issue?
Thanks for your help.
Benjamin