Problem: Using Returns Transaction Entry does not affect the costs posted to the project from the original receipt
We have a receipt which was created using a Quantity Invoiced of 0.01 instead of 1.00 (Qty Shipped is 1.00). The dollar amount used on the transaction and what the supplier was paid is correct. However, because 0.01 was used an accrual entry was created for the anticipated remaining 99% of the amount and has affected the project's costs. We do not use inventory or purchase orders, in case it matters.
Because the supplier has been paid the correct amount how do we make corrections so the project reflects the $62.68 amount instead of the $6,268.00 amount and we can relieve the accrual of $6,205.32, without affecting the supplier's activity/trial balance as they're paid-in-full and we cannot void their payment?
Thanks Yun, as was my intention but seems I failed to notice where I initiated the submission from. Thanks for pointing it out.
Hi, This seems to be a GP question, I suggest you post it to the GP's forum, I'm sure the experts there will give you good advice.
Thanks.
ZHU
Stay up to date on forum activity by subscribing. You can also customize your in-app and email Notification settings across all subscriptions.
André Arnaud de Cal... 291,151 Super User 2024 Season 2
Martin Dráb 229,963 Most Valuable Professional
nmaenpaa 101,156