Planning Worksheet -- Having to Use an Item Number Range

(6) ShareShare
ReportReport
Posted on by 3,898
Hi:
 
If you want the Planning Worksheet to generate suggestions not just for a finished good but also for its subassemblies and those subassemblies' component part numbers, you have to enter all of those items as an Item Number range in the "Calculate Plan" screen.
 
If you enter only the finished good in the Item Number "range", only one suggestion generates and that one suggestion is only for that one finished good.
 
Is there not a way of capturing all of the items without having to specify all of the Item Numbers in the range?
 
Thanks!
 
John 
I have the same question (0)
  • Suggested answer
    Mansi Soni Profile Picture
    9,069 Super User 2026 Season 1 on at
    Hello John,

    In Business Central, the Planning Worksheet suggests orders based on the item numbers specified in the Calculate Plan screen. If you only enter the finished good, it will generate a suggestion for that item alone. To include subassemblies and components without manually specifying each item, ensure that dependent demand is triggered. This typically happens when items have a Production BOM and proper replenishment settings (like Make-to-Order or Make-to-Stock). Also, check Reordering Policies and Planning Parameters to ensure the system considers all required items automatically.

    https://learn.microsoft.com/en-us/dynamics365/business-central/walkthrough-planning-supplies-automatically
    https://learn.microsoft.com/en-us/dynamics365/business-central/production-about-planning-functionality
  • Suggested answer
    Jainam M. Kothari Profile Picture
    15,959 Super User 2026 Season 1 on at
    .Hello
     
    In Business Central, to generate planning suggestions for a finished good and its subassemblies, you usually need to enter all items as an Item Number range in the "Calculate Plan" screen. However, you can streamline this by setting up a reorder cycle, defining planning parameters for items or groups (including SKUs for item, variant, and location combinations), and ensuring correct low-level codes in the Bill of Materials (BOM). These methods help include all relevant items without manually specifying each item number.
     
  • Suggested answer
    Khushbu Rajvi. Profile Picture
    22,342 Super User 2026 Season 1 on at
  • Verified answer
    Ramesh Kumar Profile Picture
    7,549 Super User 2026 Season 1 on at
    Hi John,
     
    I think best way tackle this issue is have 2 batch one for Finished and one sub assembly and defaulted to item range. I think some of the fields take default to last updated value.
     
     
    Thanks
    Ramesh
     
    If this was helpful, please check the "Does this answer your question?" box and mark it as verified.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Congratulations to the April Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Small and medium business | Business Central, NAV, RMS

#1
OussamaSabbouh Profile Picture

OussamaSabbouh 1,957 Super User 2026 Season 1

#2
YUN ZHU Profile Picture

YUN ZHU 956 Super User 2026 Season 1

#3
Teagen Boll Profile Picture

Teagen Boll 645 Super User 2026 Season 1

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans