Hello everyone
I am currently getting an issue in D365 (v10.43). Any advice in resolving this will be much appreciated. Below is the issue description.
I have a production item which has 2 operations (10 and 99) in the route. Operation 10 has setup time, process time and finally Overlap time. This operation is assigned to a resource group which has 3 resources in it.
When I originally schedule the production order/batch order for this item, 3 jobs are created for this operation and all 3 jobs are assigned to single resource within the resource group. This is correct behaviour.
But once I start Setup job for this production order, and run forward rescheduling., it sometimes changes the resource for 2nd and 3rd job to a different resource but still within the resource group. This is not correct behaviour. How can you setup one resource for an operation and then assign processing job to a different resource?
Is there a parameter which will prevent this from happening? Am I missing something?