Manufacturing Order Start Date in the Year 2003!

(1) ShareShare
ReportReport
Posted on by 3,949
Hi:
 
The Unit of Measure for each of my four Work Centers is "Hours".
 
There are thousands of hours listed in my Routing below, however, the total number of hours is less than 52 weeks.
 
Yet, when I produce a Firm Planned Production Order, its Start Date is to be back in the year 2003!  
 
This is true no matter whether the components, finished good, or Work Centers are "Backward" or "Manual" Flushing.  Why?
 
Also, even if I try "Manual" Flushing, Production makes me recalculate the Shop Calendar for my Work Centers to be for many, many years ago.  Again, why?
 
Thank you!
 
John
I have the same question (0)
  • Suggested answer
    Ben Baxter Profile Picture
    7,077 Super User 2026 Season 1 on at
    John,
    Have you established Capacity for your Work/Machine Centers?  On the Work Center list there is a Calculate Work Center Calendar, which uses each Work Center's setup options to create the daily capacity.  Be sure you have calculated the capacity for the given year and into the future.
     
    P.S. The Flushing method has nothing to do with the calculation of when a Production Order will start or finish.
     
    Best Regards,
    Ben Baxter
    Accent Software Inc
  • Suggested answer
    Jun Wang Profile Picture
    8,216 Moderator on at
    add a bit more to previous comments
     
    the main issue is to ensure the 2 things below
     
    first ensure the capacity of each work center is correctly setup. You need to ensure the calendar and work shift is correct for the work center.
    then you need to ensure the due date of the production order is correct and the qty of produced item is correct. If the capacity of the work center is small and user use backward planning for a big production order. BC will schedule the start date back to the past years. 

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Congratulations to the April Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Small and medium business | Business Central, NAV, RMS

#1
OussamaSabbouh Profile Picture

OussamaSabbouh 2,086 Super User 2026 Season 1

#2
YUN ZHU Profile Picture

YUN ZHU 1,290 Super User 2026 Season 1

#3
AndrewThomas81 Profile Picture

AndrewThomas81 1,218

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans