Production Order Status

(4) ShareShare
ReportReport
Posted on by 2,564
Hi:
 
Is it possible to change a production order's status from Released to Firm Planned?
 
John
I have the same question (0)
  • Suggested answer
    Khushbu Rajvi. Profile Picture
    19,052 Super User 2025 Season 2 on at
    Production Order Status

    once a production order is released, it cannot be directly changed back to "Firm Planned." The system does not allow reversion of the status to a previous stage like "Firm Planned" after it has been released. However, one workaround is to cancel the production order and then create a new production order with the "Firm Planned" status. Be mindful that this approach may affect any related inventory or transactions linked to the released production order.

     
  • Gerardo Rentería García Profile Picture
    22,957 Most Valuable Professional on at
    Production Order Status

    Hi, good day
    I hope this can help you, and give you some hints.

    https://yzhums.com/62785/

  • Suggested answer
    Jainam M. Kothari Profile Picture
    12,116 Super User 2025 Season 2 on at
    Production Order Status
    Hello,
     
    No, in the Standard Business Central it is not allowed to reverse the Production Order Status. You can Finish the Prod. Order from Released but Not Firm Planned.
  • Suggested answer
    M0HAN SINGH Profile Picture
    299 on at
    Production Order Status
    No, As per my knowledge it is not possible to change status from released to Firm planned. Standard BC not allow to do so. You'll require technical help to achieve this.
  • Verified answer
    Tech-Lucky Profile Picture
    1,259 Super User 2025 Season 2 on at
    Production Order Status
    No, it is generally not possible to directly change the status of a production order from Released to Firm Planned in Business Central. The standard functionality only allows moving the status forward. You cannot move a status back in the sequence. 
     

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Andrés Arias – Community Spotlight

We are honored to recognize Andrés Arias as our Community Spotlight honoree for…

Leaderboard > Small and medium business | Business Central, NAV, RMS

#1
Sumit Singh Profile Picture

Sumit Singh 2,710

#2
Sohail Ahmed Profile Picture

Sohail Ahmed 2,675 Super User 2025 Season 2

#3
Jeffrey Bulanadi Profile Picture

Jeffrey Bulanadi 2,203

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans