RE: Over Receipt Quantity Field - Reset Back to Zero
Hello, Kim.
This is a subcontracting PO, therefore it is associated to a Released Production Order.
Initially, I was not able to post the over-receipt directly on the PO, as the Released Production Order first needed to be updated to reflect the overage. In this instance, the Production Order qty was for 800 and an additional 63 were received. The Production Order was updated accordingly, and I now need to update the over-receipt qty on the PO line to only reflect the 63, but due to my initial attempts the over-receipt qty was in excess of what I need to post and I cannot change it. I can only change that value when I add a value in the qty to receive field on the PO line, which again, continues to increase the value in the over-receipt qty field. I thought that I could manually change the value in the over-receipt qty field, but I receive the error.