Hi,
A user has created a Purchase requisition that was successfully converted to a PO.
We have a batch job that confirm automatically the POs.
For an unknow reason, the Batch stopped running and displays an error message.
I checked each single distribute amount from the PO lines and all seems good.
Can you please advise what should be done
Message details
Infolog for job Purchase order confirmation GEN. (5659642782)
Infolog for task Purchase order confirmation GEN. (5665974186)
No lines for posting or quantity = 0
Posting
Purchase order: GEN-PO008151
Item number: 210-AVJY - Non-Touch
The source document lines cannot be finalized until the status is Confirmed.
The state of the source document or source document line could not be updated.
Update completed
An error occurred during update
Batch task failed: Posting
An error occurred during update
End of task log
__________
Thank you !