Is there a way to have a date in PO line that receords the originally agreed receipt date buy the supplier. Later we would update the planned receipt date to refelct the new information and /latest/ receipt date. When I change the promsied rceipt date it also updates other dates. Basically what I'm asking is, is there a date which is independant of otehr dates.
purchase order maintaining promised receipt date without any link to other dates
It already works as You describe and expect :) You just have to fill in the Promised Receipt date first.
1) Promised Receipt Date should be filled first, with the date that was agreed on. Changing this date will change other 2 dates.
2) Then You can change the Planned Receipt date - of when You actually plan to receive. It can be before or after the Promised Receipt date.
3) Expected Receipt date cannot be earlier than planned receipt date.